Zhejiang Amber Jing-Xing Natural Gas Power Generation Co., Ltd (“Jing-Xing Power Plant”) is located in Zhicheng town Changxing county in Huzhou city and is a wholly owned gas-fired power plant of the Company. Jing-Xing Power Plant was founded in January 2005 and commenced commercial operation in December 2006.

The total installed capacity is 75MW in a combined cycle gas-steam turbine generation system which consists of one gas turbine generator unit imported from Pratt & Whitney USA, with installed capacity of 55MW, one residual heat boiler and one steam turbine with 20MW output. In 2008, actual utilization hours and volume of power sales amounted to 2,443 hours and 178,715 MWh, respectively.

The plant sells its electricity to Huzhou Electric Power Bureau and its power is transmitted to the Huzhou city grid. On-grid tariff applicable to Jing-Xing Power Plant was RMB705/MWh (including VAT) effective from 20 August 2008. In addition, under the long-term supply contract between Jing-Xing Power Plant and Zhejiang province Natural Gas Development Company (“Zhejiang Gas Company”) which is responsible for the sale and distribution of natural gas transported into Zhejiang province through the West-East Gas Pipeline, Jing-Xing Power Plant will submit the expected demand for natural gas in the coming year to Zhejiang Gas Company for review by the end of each year. The contract purchase price of natural gas is determined according to the price of natural gas at delivery point implemented by Zhejiang Provincial Price Bureau from time to time.

Jing-Xing Power Plant is fuelled by natural gas and emits almost no fine particles and sulphur dioxide, and only produce a small amount of nitrogen oxide as compared to coal-fired power plants. The plant also generates less noise and lower carbon dioxide emissions compared to coal-fired power plants. For the same amount of heat, burning natural gas produces about 50% less carbon dioxide than burning coal.

Furthermore, compared to traditional coal-fired power plants, Jing-Xing Power Plant can be started up and increase electricity generation within a relatively short period of time. Thus, it can supply peak power when there is most demand for electricity from the power grid, and can capture additional power sales when there is sudden increase in demand for electricity.

 

The following table shows certain operating statistics for Jing-Xing Power Plant for each of the three years ended 31 December 2008.

  Year ended 31 December
Indicators 2006
2007
2008
Installed capacity (MW) 75 75 75
Planned utilization hours (hours) N/A 3,500 3,500
Actual utilization hours (hours) 375 3,640 2,443
Gross generation (MWh) 28,140 272,990 183,203
Power sales (MWh) (Note) 27,461 266,317 178,715
Applicable on-grid tariff at year end (RMB/MWh) 650 650 705
Actual volume of natural gas processed (thousand m3) 6,450 61,124 41,053

Note: The difference between gross generation and power sales mainly represents the internal consumption of electricity by the power plant.

 